Blackstone Hotel

 

Location: Chicago, Illinois

Contract Value: $11,000,000

Project Timeframe: 2006-2008

Summary of Work

Historical restoration of this landmark structure. Scope of work included removal and resetting of over 10,000 pieces of terra cotta, extensive masonry rebuilding and steel repairs, and building of interior block walls.

Click here to see an article on the restoration of the Blackstone Hotel
Click here to see another article on the restoration of the Blackstone Hotel

 

Project Highlight/Challenge

MARK 1 was requested to complete this project in an approximate 18 month time frame and successfully met this challenge by utilizing as many as 75 tradesmen on site at one time.

 

Contact Information

Architects:
Wiss, Janney, Elstner Associates
Office: (312) 372-0555

General Contractor:
McHugh Construction
Mr. Brian Hardy
Office: (312) 821-0300

1021 Maryland Avenue Dolton, IL 60419